Standard footwear development process and schedule

last making

1. Last performance level and development

The time it takes to develop a last could be as short as only a few weeks in the case where only a slight revision is needed to an existing, known and proven last. This time can stretch out to being several months depending on the end use of the footwear and the various complexities that arise in the shoe manufacturing process.

2. Development procedure and timeline (With the new last being finished or in line one being proved by customer)

- First prototype sample: 5 - 6 weeks after technical package is received

- Second prototype sample: 4 - 6 weeks after 1st sample feedback is received

- Salesman sample: 6 - 8 weeks after 2nd sample feedback is received

- Wear-test, Commercialisation, Production trial: From 3 - 5 months

 

Latest News

21st Feb 2008
Exciting news from Pearl Izumi on the Spring 08 run footwear... read more
25th Jan 2008
Outdoor Retailer Winter Market... read more

View all news

Testimonials

Tor Petersen - ENO
“A very professional company with a great depth of talent in regards to technical shoe making. Our dealings with TLD h...” read more

View all Testimonials